Follow the Build - November 8, 2019

 

Check out our progress at Adamo Homes with this biweekly update. From our spec homes to our semi-custom and full custom homes, there is a lot of action happening. Our team continues to work extremely hard to deliver you these Small Batch Homes! 

____________________

   

Fox Hill: Lot 26 

 This week the fireplace is complete, hardwood floor and countertops are being installed, and the cable rail is in! 

 

The Village : Copper Blush 

Move that DIRT - We have dirt moving at Copper Blush!! Prepping the the land for a home is crucial because it is the first step in creating a solid foundation. 

 

Greystone:

 

Framing is in process - working on building the "skeleton" of these townhomes! We can't wait to see how these turn out! 

 

Inspiration: 

 

Weather wrap is complete, and windows were installed this week (right image). Having snow in early October, weather wrap is a MUST. 

 

 

Check back in every other Friday for more updates!

Want more info? Call us at 303.877.4980

 

 

 

 

Share this article:

Stay in touch

Tel: (303) 877-4980

E-mail: info@adamohomes.com

Address: Castle Rock, CO 80104

 

Facebook Twitter Instagram Pinterest

Latest Tweets

Web Design and Web Development by Buildable